Demolition and new construction De Rippert 1 to 23 Holwierde

Nationaal Coördinator Groningen · Restricted · 1 lots · 271320
Type
Works
45211300
Estimated value
€ 5,80M
estimated
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The Ministry of Economic Affairs and Climate Policy, represented by the Nationaal Coördinator Groningen (NCG), is conducting a European non-public procurement for the project ‘Demolition and new construction De Rippert 1 to 23 Holwierde’. The objective is the demolition of existing structures and the realization of 12 semi-detached houses at the Holwierde location, Groningen. The procurement follows the European directive for non-public procedures (ARW 2016, Chapter 3) and requires a design and build contract with a single contractor. The contractor must have experience in dismantling, new construction, and the integration of development and construction activities, and must comply with the requirements of the European procurement rules. The assignment includes the planning, demolition, construction, and delivery of the houses, with attention to quality, safety, and sustainability.

Works · Restricted · European procedure

European
Contracting authority
Groningen
Contract type
Works
Restricted
Estimated value
€5,800,000
estimated value
Submission deadline
Ongoing
12:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Groningen, Groningen
CharacteristicsCPV 45WorksEU tenderdemolitionnew constructionsemi-detached

01What is being requested

The Ministry of Economic Affairs and Climate Policy, represented by the Nationaal Coördinator Groningen (NCG), is conducting a European non-public procurement for the project ‘Demolition and new construction De Rippert 1 to 23 Holwierde’. The objective is the demolition of existing structures and the realization of 12 semi-detached houses at the Holwierde location, Groningen. The procurement follows the European directive for non-public procedures (ARW 2016, Chapter 3) and requires a design and build contract with a single contractor. The contractor must have experience in dismantling, new construction, and the integration of development and construction activities, and must comply with the requirements of the European procurement rules. The assignment includes the planning, demolition, construction, and delivery of the houses, with attention to quality, safety, and sustainability.

The Ministry of Economic Affairs and Climate Policy, represented here by Nationaal Coördinator Groningen (NCG), welcomes you to the Mercell procurement platform for the European non-public procurement for the execution of ‘Demolition and new construction De Rippert 1 to 23 Holwierde’, consisting of 12 semi-detached houses. The NCG is looking for one contractor to enter into a design and build contract for the execution of the project ‘Demolition and new construction De Rippert 1 to 23 Holwierde’. For this purpose, the European non-public procurement for Works according to Chapter 3 ARW 2016 is

45211300€ 5,80MWorks
1Lot 1€5,800,000

02Outcome

Awarded

Plegt-Vos Noord B.V.

Award value
€5,803,616
vs. estimate
0%

03Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

04Value in context

€5,800,000

05Bidders in this segment

#Likely bidderFitWins
1Boskalis Nederland B.V.SME9669×
2KWS Infra B.V.SME9592×
3Heijmans Infra B.V.SME9565×
4Van Gelder BVSME9553×
5Dura Vermeer Infra Regionale Projecten BVSME9458×
6BAM Bouw en Techniek bvSME9134×

06Tender documents

TN404628 - SF03 Aankondiging van een gegunde opdracht 20230329101949pdfMar 29, 2023 · 25 KB
TN375609 - SF02 Aankondiging van een opdracht 20220905080613pdfSep 5, 2022 · 29 KB

07Legal themes that may be relevant here

08Frequently asked questions

Which contract form is used for this assignment?
The assignment is executed on the basis of a design and build contract with a single contractor.
What are the core tasks of the contractor within this project?
The contractor is responsible for the planning, demolition, construction, and the final delivery of the houses.

Automatically compiled from the official tender data and documents.

09Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 5,8 mln

Gegunde waarden in CPV 45 · werken n=3159