ClosedWorksRestrictedGreen

Reconstruction of Oosteres district, Groenlo

Gemeente Oost Gelre · Restricted · 1 lots · 327715
Type
Works
45200000
Estimated value
€ 2,10M
estimated
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The Municipality of Oost Gelre intends to redesign the public space in the Oosteres district in Groenlo. The current paving is worn and there is a need for a rainwater system to make the area climate-adaptive and future-proof. The procurement concerns a non-open procedure in which one contractor will be selected for both the development phase and the execution of the project. Key points are sustainability, circularity, and climate resilience. The contracting authority is looking for a partner with experience in paving works, rainwater management, and the integration of circular construction materials. The selection focuses on a total solution that meets municipal objectives both technically and sustainably.

Works · Restricted · National procedure

Sustainability counts
Contracting authority
Contract type
Works
Restricted
Estimated value
€2,100,000
estimated value
Submission deadline
Ongoing
17:00
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksGreen / SPPrainwater systemclimate adaptationsustainability

01What is being requested

The Municipality of Oost Gelre intends to redesign the public space in the Oosteres district in Groenlo. The current paving is worn and there is a need for a rainwater system to make the area climate-adaptive and future-proof. The procurement concerns a non-open procedure in which one contractor will be selected for both the development phase and the execution of the project. Key points are sustainability, circularity, and climate resilience. The contracting authority is looking for a partner with experience in paving works, rainwater management, and the integration of circular construction materials. The selection focuses on a total solution that meets municipal objectives both technically and sustainably.

The Municipality of Oost Gelre has planned a reconstruction of the public space of the Oosteres district in Groenlo. The reason for this is the condition of the paving and the desire to realize a rainwater system. This offers the opportunity to design the public space in a climate-adaptive and future-proof manner. Sustainability (including circularity) and climate resilience are key priorities. The Municipality of Oost Gelre is organizing a procurement procedure to select one contractor for the development phase of the contract and its execution.

45200000€ 2,10MWorks
1Reconstruction of Oosteres district, Groenlo€2,100,000

02Value in context

€2,100,000

03Likely competitors

#Likely bidderFitWins
1KWS Infra B.V.SME10092×
2Heijmans Infra B.V.SME10065×
3Boskalis Nederland B.V.SME10069×
4Dura Vermeer Infra Regionale Projecten BVSME10058×
5Van Gelder BVSME10053×
6NTP B.V.SME10022×

04Legal themes that may be relevant here

05Frequently asked questions

Which specific themes are central to the design of the public space?
Sustainability, circularity, and climate resilience are the central priorities in the design of the Oosteres district.
For which phases is one contractor selected?
The Municipality of Oost Gelre is organizing a procedure for the selection of one contractor who is responsible for both the development phase of the contract and its full execution.

Automatically compiled from the official tender data and documents.

06Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 2,1 mln

Gegunde waarden in CPV 45 · werken n=3159