PlannedWorksMarktconsultatie

Realization of shore power for maritime activities Beatrixhaven Eemshaven

Groningen Seaports NV · Marktconsultatie · 1 lots · 416346
Type
Works
45315100 · Electrotechnical insta
Estimated value
Not published
To deadline
Ongoing
Knock-outs
0
exclusion grounds
Award basis
Best price-quality ratio
1 criteria
Assess manuallyconfidence high

This market consultation concerns the realization of a shore power facility for approximately 14 berths in the Beatrixhaven. Groningen Seaports is looking for market parties with integrated capabilities for a two-phase approach consisting of a construction team phase and a realization phase under UAV-gc.

Works · Marktconsultatie · National procedure

Complete timeline
Contracting authority
Groningen Seaports NV
Contract type
Works
Marktconsultatie
Estimated value
Estimate not published
Submission deadline
Ongoing
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Electrotechnical installation works
Location
Netherlands
CharacteristicsCPV 45Worksshore power

01What is being requested

Realization of a public shore power facility for approximately fourteen berths in the Beatrixhaven in Eemshaven. The assignment will be executed via a two-phase approach (construction team phase followed by a realization phase) under a UAV-gc contract.

As part of the process to achieve a high-quality design and contract dossier and subsequently a sound procurement, both in terms of procedure and content, this market consultation is being held.

45315100Works
1Realization of shore power for maritime activities Beatrixhaven Eemshaven

02Strategic insight

Strategic insight · AI analysis
Focus on demonstrating integrated design and execution capabilities, as the assignment concerns a complex technical system. Prepare for a construction team phase in which collaboration and governance are crucial for the further elaboration of the preliminary design. Take into account the uncertainty regarding the grid connection by Enexis when preparing your planning and risk profile.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 5
The port remains operational during realization, which imposes requirements on phasing and safety.Important
The grid connection by Enexis is not yet fully certain regarding the timing of realization and grid capacity.Important
The system must be future-proof for variable electricity demand from offshore-related vessels.Important
The possibility is being explored for a proposal for ICT, monitoring, and power administration.Important
Execution takes place on the own premises of Groningen Seaports.Important

04Can I take part?

Technical — Possess integrated design and execution capabilities for the assignment.
Technical — Demonstrable relevant experience with electrotechnical installations, system integration, and execution in an operational port environment.

05Award criteria

Best Price-Quality Ratio (BPKV)weight n/a

The exact assessment methodology and weighting between price and quality will be determined at a later stage. Quality criteria include, among others: the approach to the integrated design process;cost control during the construction team and realization phases;risk management and planning;the implementation of the construction team collaboration and governance;sustainability.

06Process & timeline

Announcement Market Consultation incl. documents
18 maart 2026
Completing questionnaire
18 maart - 3 april 2026
Analysis of received responses to questionnaire
6 april – 10 april 2026
OPTIONAL: Sending invitation for participation in in-depth interviews
10 april 2026
OPTIONAL: Holding in-depth interviews
20 – 24 april 2026
Selection phase
Juni - augustus 2026
Tender phase
September - oktober 2026
Assessment phase
November - december 2026
Construction team phase
Januari 2027 – juni 2027
Realization phase
Juni 2027 – juni 2028
Delivery of Shore Power
Juni 2028

07Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

08Likely competitors

#Likely bidderFitWins
1Boskalis Nederland B.V.SME9769×
2Heijmans Infra B.V.SME9565×
3ENGIE Infra & Mobility B.V.SME9469×
4Dura Vermeer Infra Regionale Projecten BVSME9258×
5SPIE Nederland B.V.SME9123×
6Fa. Gebr. Van der LeeUnknown8923×

09Tender documents

TN577570 - EFE1 Vrijwillige aankondiging van voorafgaande marktconsultatie 20260318101533pdfMar 18, 2026 · 185 KB
Bijlage 2 - Verantwoordelijkheden OG-ON walstroom BeatrixhavenpdfMar 18, 2026 · 49 KB
Leidraad Marktconsultatie walstroom BeatrixhavenpdfMar 18, 2026 · 478 KB
Bijlage 1 - SchetsontwerppdfMar 18, 2026 · 1821 KB

10Legal themes that may be relevant here

11Frequently asked questions

What is the purpose of this phase in the process?
The purpose is to test the completeness of the current solidity and observation plan, to assess the integrated design and execution capabilities of market parties, and to verify the feasibility of the planned timelines.
What requirements are placed on the design and execution capacity?
Market parties must provide information regarding their integrated design and execution capacity. In addition, proof of this capacity for a comparable project is required.
How is the feasibility of the planning tested?
During this phase, it is specifically tested whether the intended planning for the realization of shore power in Beatrixhaven is realistic and feasible.
Which quality standard is mentioned for the project?
For the project, the establishment and application of quality management according to the NEN-EN-ISO 9001 standard is mentioned.

Automatically compiled from the official tender data and documents.

12Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159