ClosedWorksEuropeanOpenGreen

Realization of modifications RWZI Arnhem-Zuid

Waterschap Rivierenland · Open · 1 lots · 339851
Type
Works
45252000
Estimated value
€ 20M
estimated
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

This is a closed tender for future-proofing the RWZI Arnhem. The assignment is carried out in three work packages (Package 1, 2 and 4). The completion date is 1 February 2026.

Works · Open · European procedure

Sustainability countsEuropean
Contracting authority
Contract type
Works
Open
Estimated value
€20,000,000
estimated value
Submission deadline
Ongoing
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderGreen / SPP

01What is being requested

This is a closed tender for future-proofing the RWZI Arnhem. The assignment is carried out in three work packages (Package 1, 2 and 4). The completion date is 1 February 2026.

The operational management of the RWZI Arnhem has been facing a large number of bottlenecks for several years. The performance and availability of the installation are falling below standard, and permanent compliance with laws and regulations is not possible under current circumstances. It has been determined based on analyses that in 2035, the biological load will have increased by approximately 25% compared to the current design. The goal of the project ‘realization of modifications RWZI Arnhem’ is to future-proof the RWZI in a structured manner, so that it functions well again until at le

45252000€ 20MWorks
1Realization of modifications RWZI Arnhem-Zuid€20,000,000

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

€20,000,000

04Likely competitors

#Likely bidderFitWins
1Heijmans Infra B.V.SME10065×
2ENGIE Infra & Mobility B.V.SME10069×
3KWS Infra B.V.SME9992×
4BAM Infra B.V.SME9977×
5Dura Vermeer Infra Regionale Projecten BVSME9858×
6De Jong Zuurmond Infrabeheer, Onderhoud & Services B.V.SME9826×

05Legal themes that may be relevant here

06Frequently asked questions

Which work packages does the assignment consist of?
The assignment is divided into three work packages: Work Package 1 (sludge line) concerns modifications to the thickening, dewatering and the sludge buffer; Work Package 2 (influent reception works) concerns the realization of a new work and modification of the existing work; Work Package 4 (green gas) concerns the realization of a new green gas line.
What is the intended completion date of the works?
The intended completion date for the realization of the modifications to the RWZI Arnhem is 1 February 2026.
Which specific works fall under the sludge line (Work Package 1)?
The sludge line includes various modifications to the thickening and dewatering of primary and secondary sludge, including heat exchange, the modification of (dewatered) sludge buffer 1 and the removal of (dewatered) sludge buffer 2.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 20 mln

Gegunde waarden in CPV 45 · werken n=3159