ClosedWorksEuropeanRestricted

Realization of outdoor swimming pool Almere Stad

Gemeente Almere · Restricted · 1 lots · 420211
Type
Works
45212212 · Construction work for
Estimated value
Not published
To deadline
Ongoing
Knock-outs
1
exclusion grounds
Award basis
Best price-quality ratio
3 criteria
Assess manuallyconfidence high

This tender concerns the integrated design and realization assignment for a new outdoor swimming pool in Almere Stad under UAV-GC conditions. The award will take place based on quality (100%) with a strong focus on the preliminary design.

Works · Restricted · European procedure

European1 exclusion groundsComplete timeline
Contracting authority
Contract type
Works
Restricted
Estimated value
Estimate not published
Submission deadline
Ongoing
09:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Construction work for swimming pool
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderoutdoor swimming poolbuildingelectrical

01What is being requested

The assignment concerns the design and realization of an outdoor swimming pool in Almere Stad, including building, installation technical (E and M), demolition, and site landscaping works. Execution takes place via a UAV-GC contract type with one contractor for an estimated range between € 7 million and € 9 million.

The design and realization of the outdoor swimming pool. This concerns the building and installation technical works (electrical and mechanical (including water treatment), demolition of the hockey fields and site landscaping.

45212212Works
1Realization of outdoor swimming pool Almere Stad

02Strategic insight

Strategic insight · AI analysis
<ul Focus the core of the bid on the quality of the Preliminary Design (VO), as this carries the heaviest weight at 70%. Ensure a strong integrated approach where the coordination between building, E, and M disciplines is explicitly substantiated to manage the risks of the UAV-GC contract type. Anticipate the environmental plan activity (BOPA) and the impact of the mobility and synergy studies on the final scope.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 6
The assignment is executed under a UAV-GC contract type.Important
The assignment is an integrated assignment (design & realization) where the responsibility for coordination and interfacing lies with the contractor.Important
There is a risk of termination of the project if the required environmental permit (BOPA) is not obtained.Important
In case of termination, compensation for preparatory costs is possible up to a maximum of 12.5% of the contract sum.Important
Unstructured contact with the contracting authority is prohibited and may lead to exclusion.Important
The assignment includes no parking facilities, maintenance, or operation.Important

04Can I take part?

Financial · 1
Financial and economic standing (in accordance with the selection guidelines).Financial
Technical · 1
Technical competence, including experience requirements (references of maximum 5 years), quality monitoring, and other competencies.Technical
Exclusion ground · 1
No mandatory or optional grounds for exclusion specifically mentioned in the text, but reference to the applicability of grounds for exclusion in the UEA.Exclusion ground

05Exclusion grounds

Exclusion grounds (1)
  • No mandatory or optional grounds for exclusion specifically mentioned in the text, but reference to the applicability of grounds for exclusion in the UEA.

06Award criteria weighting

quality of the VO 70%approach to design and realization, including planning 15%sustainability 15%
Homogeneous unit (%) · sum 100% · gate passed

07Process & timeline

Publication of announcement
15 april 2026
Deadline/time for information phase, asking questions
18 mei 2026, 9.00 uur
Publication of Memorandum of Information for the information phase
22 mei 2026
Deadline/time for submitting notifications
3 juni 2026, 9.00 uur
Opening of notifications
3 juni 2026
Lottery (if necessary)
5 juni 2026
Selection intention
8 juni 2026
Suspension period
15 juni 2026
Invitation to tender
3 juli 2026
Deadline for asking questions
18 september 2026
Memorandum of Information
5 oktober 2026
Submission of tenders
19 oktober 2026
Gunningsvoornemen/beslissing
5 november 2026
Definitieve gunning
26 november 2026
Start
27 november 2026
Ontwerpfase
november 2026 – juli 2027
Bouwfase t/m oplevering
augustus 2027 – eind april 2028
Opening
1 mei 2028
Onderhoudsfase (gebrekentermijn UAV)
t/m april 2029

08Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

09Likely competitors

#Likely bidderFitWins
1Van Gelder BVSME9753×
2Combinatie Heijmans - SWARCOUnknown9573×
3KWS Infra B.V.SME9492×
4BINX Smartility B.V.SME9027×
5De Jong Zuurmond Infrabeheer, Onderhoud & Services B.V.SME8926×
6Van Doorn Geldermalsen B.V.SME8815×

10Tender documents

TN581491 - EF10 Vooraankondiging gebruikt als oproep tot mededinging - algemene richtlijn, standaardregeling 20260415133412pdfApr 16, 2026 · 208 KB
Bijlage 5 RuslandverklaringdocxApr 16, 2026 · 89 KB
Bijlage 2 Referentieblad Technische bekwaamheiddocxApr 16, 2026 · 89 KB
uea_581491_20260410143812pdfApr 16, 2026 · 587 KB
Selectieleidraad - versie 1.0(1)pdfApr 16, 2026 · 668 KB

11Legal themes that may be relevant here

12Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159