Power Transformers 110/20 kV – 90 MVA Sub-station RIEGMEER in Hoogeveen

Type
Supplies
31170000
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

N.V. RENDO, the regional utility company for Zuid-Drenthe and Noord-Overijssel, is issuing an open tender for the supply of 90 MVA power transformers 110/20 kV for the Riegmeer substation in Hoogeveen. The contract concerns supply only; installation, commissioning, and aftercare fall under the contracting authority's general terms and conditions. The technical specifications require full compliance with IEC standards and Dutch safety and environmental regulations, including a detailed testing and certification plan. Suppliers must demonstrate that they can deliver the transformers within the specified timeframe, including transport, assembly, and commissioning. Additionally, there are requirements regarding documentation, quality assurance, warranty, and after-sales support. The procedure is open, providing all interested parties an equal opportunity to submit a bid. The contract is a typical utility supply with a clear technical scope and a relatively fixed delivery sequence, resulting in an estimated moderate complexity.

Supplies · Open · European procedure

European
Contract type
Supplies
Open
Estimated value
Estimate not published
Submission deadline
Ongoing
12:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 31SuppliesEU tenderpower transformer110 kV20 kV

01What is being requested

N.V. RENDO, the regional utility company for Zuid-Drenthe and Noord-Overijssel, is issuing an open tender for the supply of 90 MVA power transformers 110/20 kV for the Riegmeer substation in Hoogeveen. The contract concerns supply only; installation, commissioning, and aftercare fall under the contracting authority's general terms and conditions. The technical specifications require full compliance with IEC standards and Dutch safety and environmental regulations, including a detailed testing and certification plan. Suppliers must demonstrate that they can deliver the transformers within the specified timeframe, including transport, assembly, and commissioning. Additionally, there are requirements regarding documentation, quality assurance, warranty, and after-sales support. The procedure is open, providing all interested parties an equal opportunity to submit a bid. The contract is a typical utility supply with a clear technical scope and a relatively fixed delivery sequence, resulting in an estimated moderate complexity.

see ITT

31170000Supplies
1Lot 1

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for leveringen is € 221.000, for reference.

04Likely competitors

#Likely bidderFitWins
1Technische Unie B.V.SME6911×
2Hitachi Energy The Netherlands BVSME66
3Fudura B.V.SME65
4Kyte Powertech LimitedUnknown64
5Lumeco BVSME63
6SÄCHSISCH-BAYERISCHE STARKSTROM-GERÄTEBAU GmbHUnknown61

05Legal themes that may be relevant here

06Frequently asked questions

What is the technical scope of the contract?
The contract concerns the supply of 90 MVA power transformers 110/20 kV for the Riegmeer substation in Hoogeveen.
What requirements apply to the technical specifications of the transformers?
The technical specifications require full compliance with IEC standards and Dutch safety and environmental regulations, including a detailed testing and certification plan.
What are the supplier's responsibilities regarding transport and installation?
Suppliers must be able to demonstrate that they can deliver the transformers within the specified timeframe, including transport, assembly, and commissioning.
What additional requirements are imposed on the delivery?
There are requirements for documentation, quality assurance, warranty, and after-sales support.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 260K
median
€ 526K
p75
€ 1,4 mln
deze opdracht

Gegunde waarden in CPV 31 · leveringen n=168