New construction MFA de Flint

Gemeente Noordenveld · Restricted · 1 lots · 349171
Type
Works
45000000
Estimated value
Not published
To deadline
Ongoing
Knock-outs
0
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence high

This concerns an integrated contract for the new construction of MFA de Flint by a building contractor including installations.

Works · Restricted · National procedure

Contracting authority
Contract type
Works
Restricted
Estimated value
Estimate not published
Submission deadline
Ongoing
12:00
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45Works

01What is being requested

The contract concerns the new construction of MFA de Flint, in which the building contractor includes the installations in an integrated contract.

Municipality of Noordenveld intends to realize a multi-purpose facility in Nietap. The building is to provide accommodation for three users: OBS De Flint (school), Kidscasa (daycare), and Stichting dorpshuis De Flint (community center). The facility will also house a multi-purpose gym. Together, these form the multi-purpose facility (MFA) De Flint.

45000000Works
1building, electrical, and mechanical realization

02Strategic insight

Strategic insight · AI analysis
Ensure that the integrated contract is well-coordinated with the intended installer. Note that the reference projects must strictly meet the requirements for new construction of utility buildings and the maximum age of five years.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 4
A corporate guarantee for the bank guarantee is not accepted.Important
The Install-Q statement only needs to be submitted at the time of tender.Important
For selection criterion S3, it is permitted to provide an ongoing project as a reference.Important
An insurance certificate is accepted as proof of insurance.Important

04Can I take part?

Technical · 3
Reference project for S3 must be a new construction of a utility building.Technical
Reference projects for technical competence may not be older than five years.Technical
The installer must comply with the Install-Q standards.Technical
Financial · 3
Mandatory AVB insurance with at least € 5,000,000.00 per event/claim (or € 2,500,000.00 direct damage and € 5,000,000.00 per year).Financial
Provide an auditor's report and annual accounts for the last 3 financial years upon request.Financial
Provide a bank guarantee of 5% running until completion.Financial

05Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

06Likely competitors

#Likely bidderFitWins
1BINX Smartility B.V.SME9727×
2Hegeman Bouw & Infra B.V.SME9331×
3Heijmans Utiliteit B.V.SME9327×
4Van Gelder BVSME9253×
5Kernbouw B.V.SME9111×
6Unica Installatietechniek B.V.SME9013×

07Tender documents

Nota van Inlichtingen 01 MFA de FlintpdfSep 27, 2024 · 79 KB
Model bankgarantiepdfSep 27, 2024 · 63 KB
Model bereidverklaring BankgarantiepdfSep 27, 2024 · 53 KB
uea_485744_20240913152825pdfSep 15, 2024 · 1340 KB
Selectieleidraad MFA De Flint (definitief 1.0)pdfSep 15, 2024 · 682 KB
Bijlage 02 ReferentieformulierenxlsxSep 15, 2024 · 34 KB
TN485744 - EF16 Aankondiging van een opdracht - algemene richtlijn, standaardregeling 20240913163843pdfSep 15, 2024 · 11 KB
Bijlage 01 Ambitie circulariteitpdfSep 15, 2024 · 7239 KB

08Legal themes that may be relevant here

09Frequently asked questions

What is the scope of the contract for the new construction of MFA de Flint?
The contract concerns the building, electrical, and mechanical realization of the works, including the building-related infrastructural facilities for ICT and the fixed interior. Additionally, the contract includes the demolition of the current school building.
Are the installations awarded as an integral part of the contract?
Yes, the tender concerns one lot in which the contractor includes the installations. It is an integrated contract.
When must the Install-Q statement be submitted?
The Install-Q statement does not need to be submitted during the selection phase, but must be submitted at the time of tender.
Which users will be accommodated in the new multi-purpose facility?
The MFA de Flint provides accommodation to OBS De Flint (school), Kidscasa (daycare), and Stichting dorpshuis De Flint (community center), supplemented by a multi-purpose gym.

Automatically compiled from the official tender data and documents.

10Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159