AwardedWorksEuropeanOpen

New construction of Integraal Kindcentrum “Landtong” - electrotechnical installations

Gemeente Amstelveen · Open · 1 lots · 266007
Type
Works
45315100
Estimated value
€ 698K
awarded
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The Municipality of Amstelveen is inviting tenders for the electrotechnical installations of a new school complex, including childcare and a gymnasium. The building comprises approximately 3,750 m² gross floor area (GFA) spread over two floors. In addition to the indoor installations, the provider must also take into account the outdoor space, the schoolyard, and the public outdoor space surrounding the complex. The municipality will provide an accessible construction route for construction traffic via an exit. The contract is subject to an open procedure and concerns a works contract. The request for quotation includes additional attachments with technical specifications and drawings.

Works · Open · European procedure

European
Contracting authority
Contract type
Works
Open
Estimated value
€698,000
awarded value
Submission deadline
Ongoing
12:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Amstelveen
CharacteristicsCPV 45WorksEU tendernew constructionelectrotechnical installationsschool complex

01What is being requested

The Municipality of Amstelveen is inviting tenders for the electrotechnical installations of a new school complex, including childcare and a gymnasium. The building comprises approximately 3,750 m² gross floor area (GFA) spread over two floors. In addition to the indoor installations, the provider must also take into account the outdoor space, the schoolyard, and the public outdoor space surrounding the complex. The municipality will provide an accessible construction route for construction traffic via an exit. The contract is subject to an open procedure and concerns a works contract. The request for quotation includes additional attachments with technical specifications and drawings.

The new construction concerns the construction of a school complex with childcare and a gymnasium. The total new construction area of the building is approximately 3,750 m² GFA across 2 floors. The schoolyard and public outdoor space surrounding the new construction will be realized by the Municipality of Amstelveen. For the entry and exit of construction traffic, the municipality provides an accessible construction route via an exit. Please refer to the Request for Quotation with attachments.

45315100Works
1Lot 1

02Outcome

Awarded

Bectro Installatietechniek

Award value
€698,000

03Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

04Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

05Bidders in this segment

#Likely bidderFitWins
1Van Gelder BVSME9453×
2Hegeman Bouw & Infra B.V.SME9231×
3BINX Smartility B.V.SME9227×
4SPIE Nederland B.V.SME9123×
5Facilicom Solutions B.V.SME8114×
6Rots Bouw B.V.SME8113×

06Tender documents

TN364809 - SF03 Aankondiging van een gegunde opdracht 20221221145232pdfDec 22, 2022 · 29 KB
220804_Nota van Inlichtingen_I&A_2022_0075pdfAug 4, 2022 · 173 KB
20220425_TO-002_Situatie nieuwpdfAug 4, 2022 · 311 KB
20220425_TO-120_Plattegrond Tweede VerdiepingpdfAug 4, 2022 · 450 KB
1503_Landtong_Amstelveen_BE_V1_20220425_RT_RegeltechniekpdfAug 4, 2022 · 1719 KB
20220425_TO-300_DoorsnedenpdfAug 4, 2022 · 2681 KB
1503_Landtong_Amstelveen_BE_V1_20220425 Kabellijst W-installatiespdfAug 4, 2022 · 2377 KB
20220425_TO-820_Plafond 2e verdiepingpdfAug 4, 2022 · 373 KB
20220425_TO-900_Vaste inrichtingpdfAug 4, 2022 · 9610 KB
20220425_TO-110_Plattegrond Eerste VerdiepingpdfAug 4, 2022 · 1025 KB
20220425_TO-200_GevelaanzichtenpdfAug 4, 2022 · 1112 KB
20220425_TO-130_DakplattegrondpdfAug 4, 2022 · 269 KB

07Legal themes that may be relevant here

08Frequently asked questions

What is the scope of the new construction to which the electrotechnical installations relate?
The new construction concerns a school complex with childcare and a gymnasium with a total area of approximately 3,750 m² GFA, spread over two floors.
What works are expected outside of the indoor installations?
In addition to the indoor installations, the provider must take into account the outdoor space, the schoolyard, and the public outdoor space surrounding the complex.
How is the accessibility for construction traffic arranged?
The Municipality of Amstelveen provides an accessible construction route for the entry and exit of construction traffic via an exit.

Automatically compiled from the official tender data and documents.

09Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 698K

Gegunde waarden in CPV 45 · werken n=3159