This market information meeting informs market parties about the upcoming dike reinforcement projects in Fryslân, with specific attention to Schiermonnikoog and the Koehool-Lauwersmeer region.

Works · Marktconsultatie · National procedure

Complete timeline
Contracting authority
Contract type
Works
Marktconsultatie
Estimated value
Estimate not published
Submission deadline
Ongoing
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45Works

01What is being requested

It concerns various projects for dike reinforcement within the Fryslân programme, including the reinforcement of the dike and dunes on Schiermonnikoog and the sub-projects of Koehool – Lauwersmeer.

On Thursday, October 3, 2024, Wetterskip Fryslân is organizing a market information meeting for the High Water Protection Program (HWBP) projects.

45000000Works
1Market Information Meeting HWBP projects Wetterskip Fryslân

02Strategic insight

Strategic insight · AI analysis
Focus on innovative solutions for construction logistics and minimizing environmental nuisance. Take into account the sustainability ambitions regarding emission-free equipment and circular materials. Prepare for an integrated approach where design and execution work closely together.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 6
The logistics on Schiermonnikoog are complex due to scale and available space.Important
Account must be taken of the breeding season and nitrogen.Important
The use of emission-free equipment and the availability of charging infrastructure is a point of attention.Important
For the Green sub-project, an Engineering & construct contract is being considered.Important
There is an ambition for climate-neutral and circular hydraulic engineering asphalt.Important
The nitrogen framework must be established for the various sub-projects.Important

04Process & timeline

Completion of exploration
Q1 2025
Plan elaboration phase
2025 t/m 2027
Selection phase
Q1/Q2 2025
Tender phase
Q3/Q4 2025
Project decision
Q2 2026
Financing realization phase
Q2 2026
Selection phase (Ternaard-Peazens Moddergat)
start Q2 2025, afronding voor de bouwvak 2025
Tender phase (Ternaard-Peazens Moddergat)
start na de bouwvak 2025
Award (Ternaard-Peazens Moddergat)
uiterlijk Q2 2026

05Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

06Likely competitors

#Likely bidderFitWins
1Boskalis Nederland B.V.SME9369×
2BAM Bouw en Techniek bvSME9134×
3Van Hattum & Blankevoort N.V.SME8919×
4Fa. Gebr. Van der LeeUnknown8923×
5SPIE Nederland B.V.SME8823×
6Vialis B.V.SME8413×

07Tender documents

Presentatie marktinformatiebijeenkomst oktober 2024pdfOct 14, 2024 · 6353 KB
TN479797 - EF04 Vooraankondiging die alleen ter informatie wordt gebruikt - algemene richtlijn 20240731163821pdfJul 31, 2024 · 6 KB

08Legal themes that may be relevant here

09Frequently asked questions

What is the purpose of the market information meeting for the HWBP projects?
The meeting serves to introduce market parties interested in projects of the Fryslân dike reinforcement programme (KLM and Schiermonnikoog), to allow them to learn about the current status of the projects and to obtain information about the procurements.
Which specific projects are covered during the meeting?
The meeting covers the dike and dune reinforcement of Schiermonnikoog, the Koehool – Lauwersmeer dike reinforcement (sub-projects KZH, Groen, and TPM) and innovation projects such as the POV-Wadden asphalt trials and Climate-neutral and Circular Hydraulic Engineering Asphalt (KCW).
What are the main challenges within the HWBP task?
Important points of attention are the financial contribution of Wetterskip Fryslân (maximum 10% of the costs), a stable schedule, sustainability ambitions, nitrogen, emission-free equipment, permits, legal issues, and the integration of societal tasks.
Which innovative aspects are addressed regarding the Schiermonnikoog dike reinforcement?
Alternative dike concepts such as a water-retaining landscape, the 'adaptive approach' pilot, stimulating salt marsh growth and dune accretion, widening the dike foundation, and anticipating drainage via outfall culverts are discussed.

Automatically compiled from the official tender data and documents.

10Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159