The Waterschap Drents Overijsselse Delta (WDODelta) is organizing a market consultation for the reinforcement of the Vecht dikes in Dalfsen and Zwolle. The dikes form a crucial part of the flood protection for the area. Following a phase of solution research, a draft preferred alternative has been prepared, which can be found at www.veiligevecht.nl. The consultation focuses on involving market parties who are willing to jointly realize the design and implementation of the project with the water board. The kick-off meeting on 22 March 2024 in Zwolle will provide an explanation of the project planning, the technical and organizational challenges, and the desired market approach. After the meeting, a written consultation round will follow, after which the water board may decide to hold individual discussions. The consultation is intended to gain insight into market perspectives, innovative ideas, and potential collaboration, with the aim of achieving an optimal, sustainable, and cost-efficient reinforcement of the Vecht dike.

Works · European procedure

European
Contract type
Works
Estimated value
Estimate not published
Submission deadline
Ongoing
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderVechtdikeflood

01What is being requested

The Waterschap Drents Overijsselse Delta (WDODelta) is organizing a market consultation for the reinforcement of the Vecht dikes in Dalfsen and Zwolle. The dikes form a crucial part of the flood protection for the area. Following a phase of solution research, a draft preferred alternative has been prepared, which can be found at www.veiligevecht.nl. The consultation focuses on involving market parties who are willing to jointly realize the design and implementation of the project with the water board. The kick-off meeting on 22 March 2024 in Zwolle will provide an explanation of the project planning, the technical and organizational challenges, and the desired market approach. After the meeting, a written consultation round will follow, after which the water board may decide to hold individual discussions. The consultation is intended to gain insight into market perspectives, innovative ideas, and potential collaboration, with the aim of achieving an optimal, sustainable, and cost-efficient reinforcement of the Vecht dike.

Market Consultation Veilige Vecht Dalfsen The dikes along the Vecht protect the area against flooding. To protect Dalfsen and Zwolle in the future as well, we are going to reinforce the Vecht dikes. Various solutions have been investigated in the recent period. There is now a proposal regarding how the dike will be reinforced: the draft preferred alternative. Please refer to the website www.veiligevecht.nl for this. The Waterschap Drents Overijsselse Delta (WDODelta) is currently also working on the market approach strategy for the design and realization of the project and would like to disc

45240000Works
1Market Consultation Veilige Vecht Dalfsen

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Likely competitors

#Likely bidderFitWins
1Boskalis Nederland B.V.SME9369×
2KWS Infra B.V.SME9292×
3Ploegam B.V.SME9222×
4Combinatie Heijmans - SWARCOUnknown9173×
5Dura Vermeer Infra Regionale Projecten BVSME9158×
6Van Oord Nederland BVSME9119×

05Legal themes that may be relevant here

06Frequently asked questions

For which parties is this market consultation primarily intended?
The consultation is primarily aimed at market parties who may be interested in further designing and realizing the project for the reinforcement of the Vecht dikes in collaboration with the Waterschap Drents Overijsselse Delta.
How does the consultation round proceed after the kick-off meeting?
Following the physical kick-off meeting on 22 March 2024 and the publication of the consultation document, a written consultation round will follow. Based on the outcomes of this written round, the water board may decide to conduct additional individual consultation discussions.
Where can information about the draft preferred alternative for the dike reinforcement be found?
Information about the draft preferred alternative, which states how the dike reinforcement will be carried out, can be found on the website www.veiligevecht.nl.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159