Market Consultation - Renewable Energy Generation on Own Lands
ProRail is conducting a market consultation to determine the strategy for renewable energy generation on its own lands. The focus lies on the feasibility of contract structures and the desired procurement method for solar and wind energy.
Supplies · Marktconsultatie · National procedure
01What is being requested
Market consultation regarding the market approach for the development of solar and wind power installations on ProRail lands. The goal is to realize 100 GWh/year of renewable energy by 2030 at the latest through various contract structures.
Market consultation within the framework of the Renewable Energy Generation on Own Lands Programme
02Strategic insight
Participation in this market consultation provides insight into future contract structures such as DBFMOO. Focus on providing reasoned explanations for the questions instead of merely yes or no. During preparation, pay attention to risk management regarding grid congestion and permitting.
03Points of attention
04Can I take part?
05Award criteria
Awarding takes place based on a weighting of various elements where the price per kWh is expected to be dominant.
The amount of power to be produced per year in MWh is factored into the award to prevent only highly favorable locations from being developed.
Outline of the approach to achieve timely successful realization, including planning and risk management.
Description of the realization period and measures for realization within congestion areas.
Description of sustainable manufacturing, assurance, sustainable disposal/processing, and compliance with ecological requirements.
Fixed price per kWh for the produced power, excluding profile and imbalance costs.
Fixed price per Guarantee of Origin (GVO).
Fixed prices per hectare for the use of lands.
06Process & timeline
07Value in context
The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for leveringen is € 221.000, for reference.
08Likely competitors
09Tender documents
10Legal themes that may be relevant here
11Frequently asked questions
What is the purpose of this market consultation?
Which technical topics are covered within the scope of the programme?
Which aspects of the market approach are addressed during the consultation?
Automatically compiled from the official tender data and documents.
12Estimated value versus the market
€ 300K
€ 691K
€ 2,0 mln
Gegunde waarden in CPV 09 · leveringen n=226