Twence B.V. is launching a market consultation for the replacement of the current steam turbine on line 3. The new turbine must meet the technical requirements of the existing installation network, including power, pressure, temperature, and efficiency, and must be compatible with the current generators and control systems. The procurement includes delivery, installation, commissioning, and aftercare, including training for operational personnel. Twence expects a detailed technical proposal, a realistic delivery and installation timeline, and a cost-effective solution that ensures operational continuity. The selection criteria focus on technical performance, industry experience, maintenance and service conditions, and total cost of ownership. The market consultation is intended to gather market information and lay the foundation for a possible future procurement.
Supplies · European procedure
01What is being requested
Twence B.V. is launching a market consultation for the replacement of the current steam turbine on line 3. The new turbine must meet the technical requirements of the existing installation network, including power, pressure, temperature, and efficiency, and must be compatible with the current generators and control systems. The procurement includes delivery, installation, commissioning, and aftercare, including training for operational personnel. Twence expects a detailed technical proposal, a realistic delivery and installation timeline, and a cost-effective solution that ensures operational continuity. The selection criteria focus on technical performance, industry experience, maintenance and service conditions, and total cost of ownership. The market consultation is intended to gather market information and lay the foundation for a possible future procurement.
This market consultation is focused on replacement of the existing Steam Turbine of Line 3.
02Exclusion grounds
- No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).
03Value in context
The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for leveringen is € 221.000, for reference.
04Likely competitors
05Legal themes that may be relevant here
06Frequently asked questions
What is the purpose of this market consultation?
What is the scope of the requested works?
What compatibility requirements apply to the new steam turbine?
Which components are part of the assignment?
Automatically compiled from the official tender data and documents.
07Estimated value versus the market
€ 300K
€ 800K
€ 4,0 mln