AwardedWorksEuropeanRestricted

European restricted tender for a construction team for the new construction of Kindcentrum (KC) Berglaren

Stichting GOO Onderwijs · Restricted · 1 lots · 359426
Type
Works
45000000
Estimated value
€ 6,70M
estimated
To deadline
Ongoing
Knock-outs
0
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence high

This European restricted tender concerns the realization of a new childcare center in Gemert by a construction team. The procedure consists of a selection phase for five candidates, followed by an award phase based on the best price-quality ratio.

Works · Restricted · European procedure

EuropeanComplete timeline
Contracting authority
Contract type
Works
Restricted
Estimated value
€6,700,000
estimated value
Submission deadline
Ongoing
12:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderconstruction teamnew constructionKindcentrum

01What is being requested

The project concerns the new construction of a Kindcentrum of approximately 2,600 m2 GFA in Gemert, whereby a construction team is responsible for developing the final design into a technical design and the ultimate realization.

The new construction of KC Berglaren must be realized by selecting and contracting a contractor(s) (or combination thereof), which, within an engineering team, develops a final design into a technical design (TO) and thereby is also offered the opportunity to realize the work. The contractor(s) (or combination thereof) is fully responsible for both the building and the installation technology parts of the assignment. The contractor(s) (or combination thereof) develops the final design into a technical design during the first phase. After completion of the technical design with the associated

45000000€ 6,70MWorks
1Restricted tender construction team€6,700,000

02Strategic insight

Strategic insight · AI analysis
Ensure a relevant reference that specifically meets the combination of education, childcare, and BSO. Check whether the minimum value of the reference projects does not fall below the threshold of € 4,000,000. In the case of a combination, pay attention to the joint and several liability of all participants.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 4
The application must contain a fully completed application form and the UEA.Important
When relying on third parties, joint and several liability is required for the execution.Important
Questions must be submitted via the messaging module of TenderNed in the prescribed format.Important
The award takes place on the basis of the best price-quality ratio.Important

04Can I take part?

Financial · 1
sufficient financial and economic standing, no known claims, no continuity clause in the latest auditor's report and appropriate insurance against professional risks.Financial
Technical · 3
one relevant reference assignment of a childcare center (education, BSO and childcare) as a member of a construction team with a size of at least 1,600 m2 GFA and a value of at least € 4,000,000 (total construction costs), carried out in the period 2009-2024, including a statement of satisfaction.Technical
possess a VCA certificate as a company or comparable certification.Technical
NEN-EN-ISO 9001:2015 certified or comparable quality management system.Technical

05Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

06Process & timeline

Invitation to apply
29 november 2024
Closing date for questions selection phase
11 december 2024
Note of instructions selection phase
18 december 2024
Deadline for application
13 januari 2025
Opening of the application vault
13 januari 2025
Notice of rejection of non-selected candidates
14 januari 2025
Invitation to tender award phase
20 januari 2025
Closing date for questions award phase 1st round
10 februari 2025
1st Note of instructions award phase
17 februari 2025
Closing date for questions award phase 2nd round
6 maart 2025
2nd Note of instructions award phase
13 maart 2025
Deadline for submission of tenders
24 maart 2025
Presentaties
31 maart 2025
Voorlopige gunning
1 april 2025
Definitieve gunning
22 april 2025
Start uitwerken definitief ontwerp tot technisch ontwerp
april 2025
Start bouw
1 oktober 2025

07Value in context

€6,700,000

08Bidders in this segment

#Likely bidderFitWins
1BINX Smartility B.V.SME9327×
2Hegeman Bouw & Infra B.V.SME9231×
3Dura Vermeer Infra Regionale Projecten BVSME9258×
4Boskalis Nederland B.V.SME9169×
5Van Gelder BVSME9153×
6Kernbouw B.V.SME8911×

09Tender documents

TN499880 - EF29 Aankondiging gegunde opdracht - algemene richtlijn, standaardregeling 20250805144049pdfAug 6, 2025 · 9 KB
Nota van inlichtingen selectiefasepdfDec 18, 2024 · 165 KB
Bijlage 2 AanmeldingsformulierdocxDec 2, 2024 · 38 KB
Bijlage 4 Uniform Europees AanbestedingsformulierpdfDec 2, 2024 · 1265 KB
Selectieleidraad KC BerglarenpdfDec 2, 2024 · 184 KB
Bijlage 3 CombinatieverklaringdocxDec 2, 2024 · 25 KB
TN499880 - EF16 Aankondiging van een opdracht - algemene richtlijn, standaardregeling 20241130115610pdfDec 2, 2024 · 9 KB
Bijlage 1 Format vragendocxDec 2, 2024 · 27 KB

10Legal themes that may be relevant here

11Frequently asked questions

What is the specific assignment description for the construction team?
The assignment concerns the selection of a contractor(s) (or combination thereof) who, in an engineering team, develops a final design into a technical design (TO) and prepares a final budget. The selected party is fully responsible for both the building and the installation technology parts.
How is the division between the engineering phase and the execution phase arranged?
In the first phase, the engineering team develops the final design into a technical design. After completion of the technical design and the final budget, a contract for the execution phase may be agreed upon, whereby the design is developed into a construction-ready design and ultimate realization.
What responsibilities rest on the contractor(s) (or combination thereof)?
The contractor(s) (or combination thereof) bears full responsibility for both the building works and the installation technology part of the new construction of Kindcentrum Berglaren.

Automatically compiled from the official tender data and documents.

12Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 6,7 mln

Gegunde waarden in CPV 45 · werken n=3159