EU-338 Line stringing and tower erection for large projects

TenneT TSO · 1 lots · 317077
Type
Works
45231400
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

TenneT TSO is launching a digital qualification procedure via Mercell to compile a list of suitable contractors for the installation of high-voltage lines and the erection of towers. The assignment includes both upgrades of existing high-voltage lines (approximately 600 km between 2026 and 2035) and the construction of new lines (approximately 400 km in the same period), representing a total demand of circa 1,000 km until 2035. The procedure focuses on line/conductor stringing and tower erection around new and existing high-voltage lines. Contractors must demonstrate experience with large-scale high-voltage projects, comply with safety and quality standards, and possess the necessary resources and personnel. The procedure is entirely digital, promoting transparency and efficiency. TenneT expects demand to be three times higher than current levels, making a robust network of partners essential.

Works · European procedure

European
Contracting authority
Contract type
Works
Estimated value
Estimate not published
Submission deadline
Ongoing
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderline stringingtower erectionhigh-voltage lines

01What is being requested

TenneT TSO is launching a digital qualification procedure via Mercell to compile a list of suitable contractors for the installation of high-voltage lines and the erection of towers. The assignment includes both upgrades of existing high-voltage lines (approximately 600 km between 2026 and 2035) and the construction of new lines (approximately 400 km in the same period), representing a total demand of circa 1,000 km until 2035. The procedure focuses on line/conductor stringing and tower erection around new and existing high-voltage lines. Contractors must demonstrate experience with large-scale high-voltage projects, comply with safety and quality standards, and possess the necessary resources and personnel. The procedure is entirely digital, promoting transparency and efficiency. TenneT expects demand to be three times higher than current levels, making a robust network of partners essential.

TenneT faces a major task in the coming years. In addition to a substantial number of upgrades to existing high-voltage overhead lines (around 600 km between 2026-2035), a substantial number of new high-voltage overhead lines is planned to be build (around 400 km between 2026-2035). This possibly leads to a total demand of 1000 km till 2035, which means a tripling (x3) of the current demand. Please note: This is the current forecast; depending on various factors, the actual number of projects may be higher or lower. With this qualification system, TenneT wishes to establish a list of suitabl

45231400Works
1EU-338 Line stringing and tower erection for large projects

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Likely competitors

#Likely bidderFitWins
1BAM Infra B.V.SME10077×
2Heijmans Infra B.V.SME9665×
3ENGIE Infra & Mobility B.V.SME9669×
4Combinatie Heijmans - SWARCOUnknown9573×
5Van Gelder BVSME9553×
6SPIE Nederland B.V.SME9223×

05Legal themes that may be relevant here

06Frequently asked questions

What is the scope of the work for the high-voltage lines?
The assignment concerns upgrades of existing high-voltage lines (approximately 600 km) and the construction of new high-voltage lines (approximately 400 km) in the period between 2026 and 2035, representing a total demand of approximately 1,000 km.
What does the qualification procedure for this assignment entail?
Through a digital qualification procedure, a list of suitable contractors is compiled for works around new and existing high-voltage lines, specifically focused on line/conductor stringing and tower erection.
Through which platform does the procurement procedure take place?
The tender procedure takes place exclusively digitally via the Mercell platform.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159