AwardedWorksEuropeanCompetitive dialogue

Dike Reinforcement Buggenum

Waterschap Limburg · Competitive dialogue · 1 lots · 278206
Type
Works
45240000
Estimated value
€ 36M
awarded
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

This project concerns the reinforcement of the dike near Buggenum, part of the High Water Protection Programme of Waterschap Limburg. The procurement is an early market approach via a competitive dialogue, aimed at realizing a two-phase agreement. Phase 1 focuses on the design, the feasibility study, and the drafting of a detailed implementation plan. Phase 2 comprises the actual construction of the dike, including hydrotechnical, civil engineering, and environmental engineering works. The contracting authority expects an integrated approach with attention to water safety, environmental and nature protection, and the minimization of disruptions for the local community. The procedure requires sound knowledge of dike and hydraulic engineering, experience with large infrastructure projects, and the ability to work within the established timelines and budgets. The tender is aimed at companies with a proven track record in water and dike construction, capable of offering innovative solutions for improving water safety.

Works · Competitive dialogue · European procedure

European
Contracting authority
Contract type
Works
Competitive dialogue
Estimated value
€36,342,133
awarded value
Submission deadline
Ongoing
17:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Roermond
CharacteristicsCPV 45WorksEU tenderdike reinforcementhigh water protectionWaterschap Limburg

01What is being requested

This project concerns the reinforcement of the dike near Buggenum, part of the High Water Protection Programme of Waterschap Limburg. The procurement is an early market approach via a competitive dialogue, aimed at realizing a two-phase agreement. Phase 1 focuses on the design, the feasibility study, and the drafting of a detailed implementation plan. Phase 2 comprises the actual construction of the dike, including hydrotechnical, civil engineering, and environmental engineering works. The contracting authority expects an integrated approach with attention to water safety, environmental and nature protection, and the minimization of disruptions for the local community. The procedure requires sound knowledge of dike and hydraulic engineering, experience with large infrastructure projects, and the ability to work within the established timelines and budgets. The tender is aimed at companies with a proven track record in water and dike construction, capable of offering innovative solutions for improving water safety.

Project dike reinforcement Buggenum is part of the High Water Protection Programme Waterschap Limburg. This project involves an early market approach to reach a two-phase agreement. This concerns a prior information notice; more information can be found in the attachments under 'Documents'.

45240000Works
1Lot 1

02Outcome

Awarded

Dura Vermeer Infra Landelijke Projecten BV

Award value
€36,342,133

03Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

04Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

05Bidders in this segment

#Likely bidderFitWins
1Dura Vermeer Infra Regionale Projecten BVSME9958×
2Heijmans Infra B.V.SME9965×
3Ploegam B.V.SME9922×
4Boskalis Nederland B.V.SME9869×
5KWS Infra B.V.SME9892×
6ENGIE Infra & Mobility B.V.SME9869×

06Tender documents

TN381612 - SF03 Aankondiging van een gegunde opdracht 20230705143850pdfJul 7, 2023 · 24 KB
Nota van inlichtingen 2022-11-22-2pdfNov 22, 2022 · 3 KB
Nota van inlichtingen 2022-11-22-1pdfNov 22, 2022 · 14 KB
TN381612 - SF14 Kennisgeving van aanvullende informatie, informatie over een onvolledige procedure of rectificatie 20221122124636pdfNov 22, 2022 · 13 KB
Nota van inlichtingen 2022-11-08-1pdfNov 8, 2022 · 3 KB
Bijlage 1 Vraagspecificatie algemeenpdfNov 7, 2022 · 1251 KB
Bijlagen A-F aanbestedingsleidraaddocxNov 7, 2022 · 88 KB
Bijlage 2 Inleiding op de overeenkomstpdfNov 7, 2022 · 347 KB
Aanbestedingsleidraad BuggenumpdfNov 7, 2022 · 1639 KB
uea_381612_20221103174628pdfNov 5, 2022 · 32 KB
TN381612 - SF02 Aankondiging van een opdracht 20221103175808pdfNov 5, 2022 · 24 KB
uea_381612_20221103174629xmlNov 5, 2022 · 122 KB

07Legal themes that may be relevant here

08Frequently asked questions

What is the structure of the agreement for this project?
The assignment is set up as an early market approach leading to a two-phase agreement. Phase 1 focuses on the design, the feasibility study, and the drafting of a detailed implementation plan. Phase 2 comprises the actual construction of the dike.
Which works will be carried out during the construction phase?
The construction of the dike includes hydrotechnical, civil engineering, and environmental engineering works within the framework of the High Water Protection Programme.
What are the main focus points during the execution of the dike reinforcement?
Execution requires an integrated approach with specific attention to water safety, environmental and nature protection, and the minimization of disruptions for the local community.

Automatically compiled from the official tender data and documents.

09Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159