ClosedWorksEuropeanCompetitive procedure with negotiationGreen

Design, construction and installation of a CO2 capture plant at HVC in Alkmaar

HVC Groep · Competitive procedure with negotiation · 1 lots · 314105
Type
Works
45252000
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The project concerns the design, construction, and installation of a CO2 storage plant at N.V. HVC in Alkmaar. HVC is a waste-to-energy plant that emits large quantities of CO2 annually. The tender focuses on an integrated solution that significantly reduces CO2 emissions, complies with Dutch and EU regulations, and integrates seamlessly with the existing infrastructure. The contractor must provide a complete technical design, including engineering, material selection, construction, installation, commissioning, and an initial operational phase. Explicit experience with CO2 capturing, waste-to-energy projects, and large industrial installations is required. The procedure is a competitive procedure with negotiation, whereby the contracting authority expects a detailed specification and a timeline of 24 to 36 months. The contractor must also submit a risk and quality management plan, a safety plan, and an environmental management plan. The tender requires a financially stable company with sufficient subcontractors and a proven track record in similar projects.

Works · Competitive procedure with negotiation · European procedure

Sustainability countsEuropean
Contracting authority
Noord-Holland
Contract type
Works
Competitive procedure with negotiation
Estimated value
Estimate not published
Submission deadline
Ongoing
14:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Alkmaar, Noord-Holland
CharacteristicsCPV 45WorksEU tenderGreen / SPPCO2 captureHVCAlkmaar

01What is being requested

The project concerns the design, construction, and installation of a CO2 storage plant at N.V. HVC in Alkmaar. HVC is a waste-to-energy plant that emits large quantities of CO2 annually. The tender focuses on an integrated solution that significantly reduces CO2 emissions, complies with Dutch and EU regulations, and integrates seamlessly with the existing infrastructure. The contractor must provide a complete technical design, including engineering, material selection, construction, installation, commissioning, and an initial operational phase. Explicit experience with CO2 capturing, waste-to-energy projects, and large industrial installations is required. The procedure is a competitive procedure with negotiation, whereby the contracting authority expects a detailed specification and a timeline of 24 to 36 months. The contractor must also submit a risk and quality management plan, a safety plan, and an environmental management plan. The tender requires a financially stable company with sufficient subcontractors and a proven track record in similar projects.

Design, construction and installation of a CO2 capture plant at HVC in Alkmaar

45252000Works
1Lot 1

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Likely competitors

#Likely bidderFitWins
1Den Ouden Aannemingsbedrijf B.V.SME8923×
2NTP B.V.SME8922×
3BAM Bouw en Techniek bvSME8934×
4Croonwolter&dros B.V.SME8825×
5Boskalis Nederland B.V.SME8769×
6BINX Smartility B.V.SME8727×

05Tender documents

TN435513 - SF02 Aankondiging van een opdracht 20231021140446pdfOct 21, 2023 · 28 KB

06Legal themes that may be relevant here

07Frequently asked questions

What is the scope of the contract for the CO2 storage plant?
The contract includes the complete process of design, engineering, material selection, construction, installation, and commissioning of a CO2 capture plant at HVC in Alkmaar.
What specific expertise is expected from the contractor?
The contractor must have experience with CO2 capturing, waste-to-energy projects, and the realization of large industrial installations.
Which plans must be submitted as part of the contract?
The contractor must submit a risk and quality management plan, a safety plan, and an environmental management plan.
What is the expected lead time of the project?
The contracting authority expects a timeline of 24 to 36 months for the execution of the project.

Automatically compiled from the official tender data and documents.

08Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159