Budget RFP Power transformers 110/20kV 90 MVA for the new substation RIEGMEER in Hoogeveen, the Netherlands
RENDO, together with TenneT, is building a new 110/20kV substation at the RIEGMEER industrial estate in Hoogeveen. The first phase, planned for Q2 2027, requires three 110/20kV 90 MVA transformers providing an N-1 capacity of 180 MVA. The installation is designed with expansion options up to 360 MVA N-1 via two additional transformers. The tender focuses on delivery, installation, and aftercare, with an emphasis on quality, safety, and compliance with Dutch and European standards. Suppliers must demonstrate that they can guarantee the technical, logistical, and operational requirements, including collaboration with TenneT and the RENDO team.
Supplies · European procedure
01What is being requested
RENDO, together with TenneT, is building a new 110/20kV substation at the RIEGMEER industrial estate in Hoogeveen. The first phase, planned for Q2 2027, requires three 110/20kV 90 MVA transformers providing an N-1 capacity of 180 MVA. The installation is designed with expansion options up to 360 MVA N-1 via two additional transformers. The tender focuses on delivery, installation, and aftercare, with an emphasis on quality, safety, and compliance with Dutch and European standards. Suppliers must demonstrate that they can guarantee the technical, logistical, and operational requirements, including collaboration with TenneT and the RENDO team.
To facilitate the energy transition, RENDO and TenneT will realize a new 110/20kV substation near the city of Hoogeveen on the RIEGMEER industrial estate (hereinafter called the Project). The total project scope is given in attachment A. The realization and delivery of the first phase is planned for Q2 2027. In the first phase, a capacity of 180 MVA N-1 will be available based on three (3) power transformers of 110/20kV 90MVA with expansion options up to 360 MVA N-1, based on two (2) additional power transformers onwards.
02Exclusion grounds
- No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).
03Value in context
The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for leveringen is € 221.000, for reference.
04Likely competitors
05Tender documents
06Legal themes that may be relevant here
07Frequently asked questions
What is the technical specification of the transformers for the RIEGMEER project?
What capacity will be realized in the first phase of the project?
Are there possibilities for expanding the transformer capacity?
When is the realization of the first phase planned?
Automatically compiled from the official tender data and documents.
08Estimated value versus the market