AwardedWorksRestricted

Construction team transformation school building Beatrijsstraat 8-12 Den Haag

Gemeente Den Haag · Restricted · 1 lots · 275529
Type
Works
45000000
Estimated value
€ 25K
awarded
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The Municipality of Den Haag wishes to enter into a construction team agreement for the project 'Bouwteam transformatie schoolgebouw Beatrijsstraat 8-12'. The contract is a two-phase contract: in phase one, the contractor/advisor provides design procedures, advice, and expertise; in phase two, they receive the right of first refusal for the execution. The contracting authority requests a construction team in which the contractor participates in the design process as an advisor and performs various design and advisory works. Following the design phase, the contractor has the right of first refusal for the execution. The construction team agreement may optionally be followed by a works contract. The procedure is non-public and no CPV code has been specified. The procurement concerns a works-type assignment for a school building in Den Haag. The focus lies on collaboration, knowledge sharing, and an integrated approach to design and execution.

Works · Restricted · National procedure

Contracting authority
Contract type
Works
Restricted
Estimated value
€25,000
awarded value
Submission deadline
Ongoing
09:00
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Location
Den Haag
CharacteristicsCPV 45Worksconstruction teamtwo-phase contractschool building

01What is being requested

The Municipality of Den Haag wishes to enter into a construction team agreement for the project 'Bouwteam transformatie schoolgebouw Beatrijsstraat 8-12'. The contract is a two-phase contract: in phase one, the contractor/advisor provides design procedures, advice, and expertise; in phase two, they receive the right of first refusal for the execution. The contracting authority requests a construction team in which the contractor participates in the design process as an advisor and performs various design and advisory works. Following the design phase, the contractor has the right of first refusal for the execution. The construction team agreement may optionally be followed by a works contract. The procedure is non-public and no CPV code has been specified. The procurement concerns a works-type assignment for a school building in Den Haag. The focus lies on collaboration, knowledge sharing, and an integrated approach to design and execution.

The scope of the assignment concerns entering into a so-called “two-phase contract” in the form of a construction team, whereby the contractor participates as an advisor in the elaboration and completion of the design process and performs various design and advisory works, contributing expertise and holding the right of first refusal for the execution of the works after the design process. For the purpose of this project, the contracting authority wishes to enter into a construction team agreement, after which, optionally, the works contract can be awarded. See the selection guide for more inf

45000000Works
1Lot 1

02Outcome

Awarded

Dura Vermeer Bouw Heyma BV

Award value
€25,000

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Bidders in this segment

#Likely bidderFitWins
1Combinatie Heijmans - SWARCOUnknown9973×
2Heijmans Infra B.V.SME9965×
3Dura Vermeer Infra Regionale Projecten BVSME9958×
4BAM Infra B.V.SME9977×
5KWS Infra B.V.SME9792×
6BAM Bouw en Techniek bvSME9734×

05Legal themes that may be relevant here

06Frequently asked questions

What does the contract form of this assignment entail?
A two-phase contract in the form of a construction team is concluded. In phase one, the contractor performs design and advisory works as an advisor and contributes expertise during the design process. In phase two, the contractor has the right of first refusal for the execution of the works.
Can the construction team agreement be extended with a works contract?
Yes, after concluding the construction team agreement, a works contract can optionally be awarded for the execution of the works.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 25K

Gegunde waarden in CPV 45 · werken n=3159