ClosedWorksOpen

Specification 2465 N831 Heusden - Well

Provincie Gelderland · Open · 361223
Type
Works
45233120
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

Provincie Gelderland is using an open procedure for extensive roadworks at the Heusden – Well location. The project includes, among other things, the excavation and processing of approximately 4,800 m³ of soil, the breaking up and re-laying of foundations, asphalt and concrete paving, and various modular paving elements. Additionally, curbings, traffic markings, signage, and guardrails will be removed and installed. The work also requires moving light points, an NBD mast, and implementing traffic measures. The works are divided into several phases, with a total area of more than 35,000 m² for asphalt paving and additional works in the field of lighting and traffic safety. The contracting authority expects an integrated approach, in which quality, safety, and minimal disruption to traffic are central. The tender focuses on a reliable contractor with experience in road and infrastructure projects, capable of delivering within the specified timeframes and budgets.

Works · Open · National procedure

Contracting authority
Contract type
Works
Open
Estimated value
Estimate not published
Submission deadline
Ongoing
12:00
Scope
National
National procedure
Lots
Single contract
Main CPV code
Location
Netherlands
CharacteristicsCPV 45Worksroadworkspavingasphalt

01What is being requested

Provincie Gelderland is using an open procedure for extensive roadworks at the Heusden – Well location. The project includes, among other things, the excavation and processing of approximately 4,800 m³ of soil, the breaking up and re-laying of foundations, asphalt and concrete paving, and various modular paving elements. Additionally, curbings, traffic markings, signage, and guardrails will be removed and installed. The work also requires moving light points, an NBD mast, and implementing traffic measures. The works are divided into several phases, with a total area of more than 35,000 m² for asphalt paving and additional works in the field of lighting and traffic safety. The contracting authority expects an integrated approach, in which quality, safety, and minimal disruption to traffic are central. The tender focuses on a reliable contractor with experience in road and infrastructure projects, capable of delivering within the specified timeframes and budgets.

General description The work mainly consists of: a. Excavation and processing of soil; quantity approx. 4,800 m3 b. Breaking up foundation; quantity approx. 1,810 m2 c. Laying foundation; quantity approx. 2,095 m2 d. Milling asphalt paving; quantity approx. 35,260 m2 e. Breaking up asphalt paving; quantity approx. 1,450 m2 f. Sawing asphalt paving; quantity approx. 1,460 m g. Laying asphalt paving; quantity approx. 4,465 tons h. Breaking up concrete paving; quantity approx. 40 m2 i. Laying concrete paving; quantity approx. 105 m2 j. Breaking up modular paving; quantity appro

45233120Works

02Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

03Likely competitors

#Likely bidderFitWins
1KWS Infra B.V.SME10092×
2Van Gelder BVSME10053×
3De Jong Zuurmond Infrabeheer, Onderhoud & Services B.V.SME10026×
4BAM Infra B.V.SME9977×
5Boskalis Nederland B.V.SME9969×
6Gebr. van Kessel Wegenbouw B.V.SME9920×

04Frequently asked questions

What are the most important works carried out in this contract?
The contract includes, among other things, the excavation and processing of approximately 4,800 m³ of soil, the milling of approximately 35,260 m² of asphalt paving, the laying of approximately 4,465 tons of asphalt, and the laying of approximately 1,165 m² of modular paving.
Which works regarding traffic facilities and lighting are part of the contract?
The work includes the removal and installation of signage (109 units removed, 47 units installed), moving 7 light points and 1 NBD mast, laying 11 km of longitudinal markings, and implementing traffic measures.
What is the scope of the works for the foundation and curbings?
The works include breaking up approximately 1,810 m² of foundation and laying approximately 2,095 m² of foundation. Additionally, approximately 205 m1 of curbings must be broken up and approximately 1,115 m1 of curbings must be installed.

Automatically compiled from the official tender data and documents.

05Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159