AwardedServicesEuropeanOpen
Provision of collection resources, receipt and processing of metals NV BAR Afvalbeheer
5
5 of 6 core insights found
Measures presence, not accuracy · documents remain authoritative
ScopeAdvicePoints of attentionSuitability requirementsAward criteriaTimeline
Type
Services
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
2 criteria
Assess manuallyconfidence high
This tender concerns the collection and processing of metals for the Groot-Rijnmond region. The assignment has an initial duration of two years with options for two extensions.
Services · Open · European procedure
EuropeanComplete timeline
CharacteristicsCPVServicesEU tendercollection resourcesmetalsprocessing
01What is being requested
The assignment concerns the provision of collection resources, the receipt and the processing of metals for NV BAR Afvalbeheer with an initial duration of 24 months.
Provision of collection resources, receipt and processing of metals NV BAR Afvalbeheer.
02Outcome
Awarded
HKS Metals
Bidders
3
03Strategic insight
Strategic insight · AI analysis
Focus on the qualitative award criteria as described in Annex 4. Ensure a competitive tender price as both criteria have a maximum score of 100 points. Take into account the unilateral extension rights of the contracting authority.
04Points of attention
Important · 4
The agreement can be extended a maximum of 2 times by 12 months.Important
The extension is not automatic or tacit.Important
The tender must remain valid for at least 3 months.Important
Electronic submission is required via TenderNed.Important
05Exclusion grounds
Exclusion grounds — consult the ESPD
- No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).
06Award criteria
Quality100 punten
See section “1. Qualitative award criteria” in Annex 4 of the procurement documents.
Price100 punten
See section “2. Tender price” in Annex 4 of the procurement documents.
07Process & timeline
Deadline for requests for additional information
14/10/2025 10:00 +02:00
Deadline for receipt of tenders
11/11/2025 10:00 +01:00
Opening date
11/11/2025 11:05 +01:00
Start date
01/02/2026
End date of the duration
31/01/2028
08Value in context
Estimate not published
The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for diensten is € 221.000, for reference.
09Bidders in this segment
#Likely bidderFitWins
1HKS Scrap Metals B.V. potentialSME400×
2Renewi Nederland B.V. potentialSME400×
3A & M Recycling B.V. potentialSME350×
4SITA Recycling Services Zuid potentialUnknown350×
5Den Ouden Organic B.V. potentialSME350×
6RetourMatras B.V. potentialSME350×
10Tender documents
TN547643 - EF29 Aankondiging gegunde opdracht - algemene richtlijn, standaardregeling 20260113091651pdfJan 14, 2026 · 144 KB
Nota van inlichtingen metalen 15-10-2025zipOct 15, 2025 · 191 KB
Aanbestedingsdocumenten metalen NV BAR AfvalbeheerzipSep 25, 2025 · 2265 KB
TN547643 - EF16 Aankondiging van een opdracht - algemene richtlijn, standaardregeling 20250924121812pdfSep 25, 2025 · 10 KB
11Legal themes that may be relevant here
Advies 426> Het betreft een Europese openbare procedure voor WMO-vervoer, leerlingenvervoer, participatiewetvervoer en lokaal vervoer, plus Advies 111> Europese openbare aanbestedingsprocedure voor vogeltellingen. Als een door de aanbestedende dienst betrokken beoordelaar op de vAdvies 290> Meervoudig onderhandse aanbesteding van RAW-raamovereenkomst met een looptijd van één jaar voor rioolreiniging en rioolinspectieAdvies 439> Europese openbare procedure voor een raamovereenkomst voor diensten betreffende het vervoer van stoffelijke overschotten. De opdAdvies 84> Openbaar nationale aanbestedingsprocedure voor een raamovereenkomst voor vertaaldiensten. IIB dienst en gebondenheid aan algemen
12Frequently asked questions
What is the expected duration of the agreement?
The agreement has an initial duration of 24 months, from 1 February 2026 up to and including 31 January 2028.
In what manner can the agreement be extended?
The contracting authority has the right to unilaterally extend the agreement twice with periods of 12 months, until at the latest 31 January 2030.
Automatically compiled from the official tender data and documents.