AI 2024-0046 - Conversion of sports field lighting

Gemeente Amsterdam · Open · 1 lots · 356613
Type
Works
45000000
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The Municipality of Amsterdam intends to convert all sports fields within a single sports park from conventional lighting installations to dimmable LED systems. The project consists of a preparation sub-assignment and a realization sub-assignment. Key activities include the inventory of existing installations, the preparation of lighting calculations, coordinating the connection with Liander, installing LED masts and dynamic control systems, redistributing electrical supplies, configuring and commissioning the new systems, and the testing, inspection, and delivery of as-built drawings. The assignment requires a combination of building, electrical, and ICT skills, as well as experience with sports field lighting and cooperation with network municipalities.

Works · Open · National procedure

Contracting authority
Contract type
Works
Open
Estimated value
Estimate not published
Submission deadline
Ongoing
14:00
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45Workssports field lightingLEDdimmable

01What is being requested

The Municipality of Amsterdam intends to convert all sports fields within a single sports park from conventional lighting installations to dimmable LED systems. The project consists of a preparation sub-assignment and a realization sub-assignment. Key activities include the inventory of existing installations, the preparation of lighting calculations, coordinating the connection with Liander, installing LED masts and dynamic control systems, redistributing electrical supplies, configuring and commissioning the new systems, and the testing, inspection, and delivery of as-built drawings. The assignment requires a combination of building, electrical, and ICT skills, as well as experience with sports field lighting and cooperation with network municipalities.

The scope of one preparation sub-assignment and one realization sub-assignment will consist of all sports fields to be converted within one sports park. The work mainly consists of: - The preparation of sub-assignments; - The inventory of existing conventional sports field lighting installations; - The preparation of calculations for lighting, cables, and light masts including foundations; - The coordination and application for the connection at the Liander supply point; - The conversion of conventional to dimmable LED sports field lighting installations; - The installation of switching and d

45000000Works
1AI 2024-0046 - Conversion of sports field lighting€0

02Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

03Likely competitors

#Likely bidderFitWins
1Heijmans Infra B.V.SME9665×
2Combinatie Heijmans - SWARCOUnknown9573×
3Dura Vermeer Infra Regionale Projecten BVSME9558×
4BAM Bouw en Techniek bvSME9334×
5BINX Smartility B.V.SME9327×
6Boskalis Nederland B.V.SME9369×

04Legal themes that may be relevant here

05Frequently asked questions

What is the content of the preparation sub-assignment?
The preparation includes the preparation of sub-assignments, the inventory of existing conventional sports field lighting installations, and the preparation of calculations for lighting, cables, and light masts including foundations.
What does the realization sub-assignment entail?
The realization includes the conversion of conventional to dimmable LED sports field lighting installations, the installation of switching and distribution devices with dynamic control systems, the configuration, testing, inspection, and the delivery of as-built drawings and a delivery dossier.
Which activities are carried out regarding the electrical infrastructure?
The activities include coordinating and applying for the connection at the Liander supply point, untangling existing electrical supplies in club buildings, and realizing new supply points.
What is the scope of the sub-assignments?
The scope of one preparation sub-assignment and one realization sub-assignment consists of all sports fields to be converted within one sports park.

Automatically compiled from the official tender data and documents.

06Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159