ClosedWorksEuropeanCompetitive procedure with negotiation

Installation of 1,300 m sheet piling in Rozenburg

Havenbedrijf Rotterdam NV · Competitive procedure with negotiation · 1 lots · 322085
Type
Works
45262212
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

Havenbedrijf Rotterdam NV has issued a tender for the installation of a 1,300-meter-long sheet piling wall in Rozenburg. The sheet piling must be placed parallel to the Droespolderweg, within an existing pipeline corridor, to enable future expansions of cables and pipelines. A former railway embankment is located only 1.5 meters away, meaning the expansion can only be realized through a sheet piling construction that stabilizes the embankment, allowing part of the embankment to be excavated. The assignment includes participation in the construction team, the placement of the sheet piling, the installation of anchors over the entire length, and the excavation of the embankment. The procedure is a competitive procedure with negotiation, aimed at a reliable, technically competent, and financially stable company. The contracting authority expects a project with high safety and environmental standards, a clear schedule, and an integrated approach with the existing infrastructure.

Works · Competitive procedure with negotiation · European procedure

European
Contracting authority
Contract type
Works
Competitive procedure with negotiation
Estimated value
Estimate not published
Submission deadline
Ongoing
14:00
Scope
European
European procedure
Lots
1
1 lots
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tendersheet pilingpipeline corridorRozenburg

01What is being requested

Havenbedrijf Rotterdam NV has issued a tender for the installation of a 1,300-meter-long sheet piling wall in Rozenburg. The sheet piling must be placed parallel to the Droespolderweg, within an existing pipeline corridor, to enable future expansions of cables and pipelines. A former railway embankment is located only 1.5 meters away, meaning the expansion can only be realized through a sheet piling construction that stabilizes the embankment, allowing part of the embankment to be excavated. The assignment includes participation in the construction team, the placement of the sheet piling, the installation of anchors over the entire length, and the excavation of the embankment. The procedure is a competitive procedure with negotiation, aimed at a reliable, technically competent, and financially stable company. The contracting authority expects a project with high safety and environmental standards, a clear schedule, and an integrated approach with the existing infrastructure.

A pipeline corridor runs parallel to the Droespolderweg in Rozenburg. To accommodate future expansions regarding cables and pipelines, the pipeline corridor must be widened by several meters here. However, adjacent to this pipeline corridor, within approximately 1.5 m, lies a former railway embankment, which means the expansion must be realized through the application of a sheet piling construction in the embankment, so that part of the embankment can be excavated. The length of the route is approximately 1,350 m. The project scope consists of: Participating in the construction team; Install

45262212Works
1Installation of 1,300 m sheet piling in Rozenburg

02Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Likely competitors

#Likely bidderFitWins
1Boskalis Nederland B.V.SME9869×
2Heijmans Infra B.V.SME9865×
3KWS Infra B.V.SME9592×
4BAM Infra B.V.SME9577×
5Combinatie Heijmans - SWARCOUnknown9373×
6ENGIE Infra & Mobility B.V.SME9369×

05Legal themes that may be relevant here

06Frequently asked questions

What is the exact scope of the works?
The assignment includes the installation of 1,300 meters of sheet piling, the installation of anchors over the entire length of the sheet piling, and the excavation of the embankment.
What is the purpose of the sheet piling construction in Rozenburg?
The sheet piling construction serves to widen the pipeline corridor parallel to the Droespolderweg for future expansions of cables and pipelines, whereby part of the former railway embankment can be excavated.
How must the contracting authority be supported during execution?
The contractor must participate in the construction team for the realization of the sheet piling construction and the associated works.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159