615.10.01.RE Deense Hoek Junction Hmp 3.3 to 3.8 Construction Team and Realisation

Provincie Noord-Brabant · Open · 1 lots · 411184
Type
Works
45220000 · Civil engineering work
Estimated value
Not published
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence moderate

The Province of Noord-Brabant is looking for a partner for the construction team phase and realisation of the Deense Hoek roundabout, whereby the contractor is responsible for the execution design and the execution.

Works · Open · National procedure

Complete timeline
Contracting authority
Contract type
Works
Open
Estimated value
Estimate not published
Submission deadline
Ongoing
10:00
Scope
National
National procedure
Lots
1
1 lots
Main CPV code
Civil engineering works and construction works
Location
Netherlands
CharacteristicsCPV 45WorksConstruction TeamRealisationRoundabout

01What is being requested

The contract concerns participation in a construction team and the final realisation of a roundabout at the N615 - Deense Hoek junction, including the development of an execution design and the associated RAW specification.

The province of Noord-Brabant intends to award a contract for the construction team phase and the realisation of project 615.10.01.RE: 615.10 Deense Hoek Junction Hmp 3.3 to 3.8. The contract includes the participation of the contractor in a construction team, with the aim of delivering specification/execution drawings and a RAW specification. The contractor is the intended performer for the final realisation of the project. The objective of the project consists of: Realisation of a roundabout at the N615 - Deense Hoek junction including connections to the adjacent roads. Including possible

45220000Works
1615.10.01.RE 'Deense Hoek Junction Hmp 3.3 to 3.8' Construction Team and Realisation

02Strategic insight

Strategic insight · AI analysis
Focus on active collaboration within the construction team to integrate the requirements from the KES. Ensure a technically sound design where the manufacturability falls entirely under your own responsibility.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 3
The contractor is integrally responsible for the interpretation of investigations and the technical manufacturability of the design.Important
Any errors in the design are at the risk of the contractor, even if these were established in consensus within the construction team.Important
There is a deviation from the provisions of the UAV-2012 (version 2025) as will be explicitly included in the specification.Important

04Process & timeline

Start of tender
31 maart 2026
Register for General Information
3 april 2026
General Information meeting
7 april 2026
Period for requests for additional information
11 mei 2026
Deadline for submission
2 juni 2026
Provisional award
3 juli 2026
Start date
01/08/2026
End date of duration
31/12/2027

05Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

06Likely competitors

#Likely bidderFitWins
1Heijmans Infra B.V.SME10065×
2BAM Infra B.V.SME9977×
3Dura Vermeer Infra Regionale Projecten BVSME9958×
4Den Ouden Aannemingsbedrijf B.V.SME9923×
5KWS Infra B.V.SME9892×
6Boskalis Nederland B.V.SME9869×

07Tender documents

615.10 - rectificatie - datum en tijdstip algemene inlichtingenbijeenkomst 6291909pdfMar 16, 2026 · 57 KB
uea_570205_20260205094047pdfFeb 5, 2026 · 339 KB
TN570205 - EFE2 Vrijwillige vooraankondiging 20260205163012pdfFeb 5, 2026 · 140 KB

08Legal themes that may be relevant here

09Frequently asked questions

What is the content of the assignment?
The contract includes participation in a construction team to deliver specification/execution drawings and a RAW specification, followed by the realisation of a roundabout at the N615 - Deense Hoek junction, including connections to adjacent roads and a possible connection of the SFR.
When does the general information meeting take place?
The General Information meeting is scheduled for Monday 6 April 2026 from 11:00 to 12:00.
What is the intended timeframe for the realisation of the works?
The realisation of all works must be completed in the summer of 2027.

Automatically compiled from the official tender data and documents.