ClosedWorksOnderhandeling zonder bekendmaking

31146467: Announcement of a modification Design and replacement of Hoog Burel viaduct

Rijkswaterstaat Programma's, Projecten en Onderhoud · Onderhandeling zonder bekendmaking · 250688
Type
Works
45221121
Estimated value
€ 22K
awarded
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

Rijkswaterstaat is requesting a full replacement of the Hoog Burel viaduct (object 33A-109-01) west of Apeldoorn, over the A1. The structure is located within a Natura 2000 area, meaning environmental requirements play a crucial role. The new construction must be suitable for all traffic classes, comply with the already established client and safety standards, and guarantee a service life of 100 years. The project includes abutments, piers, a complete deck and railings, and requires integration into the A1 system with attention to the aesthetic program of requirements (EPvE) and the applicable road design guidelines. The procedure is negotiations without publication, which means limited competition.

Works · Onderhandeling zonder bekendmaking · National procedure

Contract type
Works
Onderhandeling zonder bekendmaking
Estimated value
€21,757
awarded value
Submission deadline
Ongoing
Scope
National
National procedure
Lots
Single contract
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksviaductHoog BurelNatura 2000

01What is being requested

Rijkswaterstaat is requesting a full replacement of the Hoog Burel viaduct (object 33A-109-01) west of Apeldoorn, over the A1. The structure is located within a Natura 2000 area, meaning environmental requirements play a crucial role. The new construction must be suitable for all traffic classes, comply with the already established client and safety standards, and guarantee a service life of 100 years. The project includes abutments, piers, a complete deck and railings, and requires integration into the A1 system with attention to the aesthetic program of requirements (EPvE) and the applicable road design guidelines. The procedure is negotiations without publication, which means limited competition.

This concerns the Hoog Burel viaduct – object 33A-109-01, located west of Apeldoorn and running over Rijksweg A1. The object is located in a Natura 2000 area. The project provides for the total replacement of the existing structure so that a new connection is available that: * is suitable for all traffic classes; * complies with the client requirements already gathered; * is reliable, available, maintainable, and safe for a period of 100 years. It concerns the overall new construction of the viaduct: abutments, piers and (complete) deck, including railings. Furthermore, the necessary measures

45221121Works

02Outcome

Awarded

Dura Vermeer Divisie Infra BV

Award value
€21,757

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Bidders in this segment

#Likely bidderFitWins
1BAM Infra B.V.SME10077×
2KWS Infra B.V.SME9892×
3Boskalis Nederland B.V.SME9869×
4Heijmans Infra B.V.SME9865×
5Combinatie Heijmans - SWARCOUnknown9773×
6Dura Vermeer Infra Regionale Projecten BVSME9758×

05Legal themes that may be relevant here

06Frequently asked questions

What is the scope of the works for the Hoog Burel viaduct?
The project includes the overall new construction of the viaduct (object 33A-109-01), consisting of abutments, piers, a complete deck and railings.
What technical requirements must the new construction meet?
The new connection must be suitable for all traffic classes, comply with the gathered client requirements, and be reliable, available, maintainable, and safe for a period of 100 years.
Which specific guidelines apply to the integration of the viaduct?
The viaduct must be integrated into the A1 system, taking into account the aesthetic program of requirements (EPvE) A1 and the current road design laws and regulations.
Which environmental conditions are important for this project?
The Hoog Burel viaduct is located in a Natura 2000 area.

Automatically compiled from the official tender data and documents.

07Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
deze opdracht

Gegunde waarden in CPV 45 · werken n=3159