AwardedWorksOpen

22602 Cooling & expansion of data network building A165 Camp New Amsterdam

Rijksvastgoedbedrijf · Open · 266091
Type
Works
45000000
Estimated value
€ 3,51M
awarded
To deadline
Ongoing
Knock-outs
n/a
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence low

The Rijksvastgoedbedrijf (RVB) intends to tender for the installation of a new cooling and data network in building A165, Camp New Amsterdam. The project includes the design, supply, installation, and testing of an efficient cooling system for critical IT infrastructure, as well as the expansion of the existing data network with additional switches, cables, and redundant connections. The works must comply with Dutch safety and energy efficiency standards, including ISO 27001 compatibility for data security and the latest energy-efficient cooling technologies. The contracting authority expects a detailed project plan, schedule, cost estimate, and a maintenance contract. The tender is open, allowing all interested companies to submit a bid. The RVB emphasizes that the execution must align with the ministry's sustainability objectives, with a focus on CO2 reduction and minimizing the ecological footprint.

Works · Open · National procedure

Contracting authority
Contract type
Works
Open
Estimated value
€3,510,000
awarded value
Submission deadline
Ongoing
10:00
Scope
National
National procedure
Lots
Single contract
Main CPV code
Location
Netherlands
CharacteristicsCPV 45Workscoolingdata networkbuilding

01What is being requested

The Rijksvastgoedbedrijf (RVB) intends to tender for the installation of a new cooling and data network in building A165, Camp New Amsterdam. The project includes the design, supply, installation, and testing of an efficient cooling system for critical IT infrastructure, as well as the expansion of the existing data network with additional switches, cables, and redundant connections. The works must comply with Dutch safety and energy efficiency standards, including ISO 27001 compatibility for data security and the latest energy-efficient cooling technologies. The contracting authority expects a detailed project plan, schedule, cost estimate, and a maintenance contract. The tender is open, allowing all interested companies to submit a bid. The RVB emphasizes that the execution must align with the ministry's sustainability objectives, with a focus on CO2 reduction and minimizing the ecological footprint.

[...take the text from paragraph 2.1.1 of the procurement registration phase guidelines...]

45000000Works

02Outcome

Awarded

EQUANS West-Nederland B.V.

Award value
€3,510,000

03Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

04Bidders in this segment

#Likely bidderFitWins
1BAM Bouw en Techniek bvSME9434×
2Heijmans Utiliteit B.V.SME9427×
3Heijmans Infra B.V.SME9365×
4BINX Smartility B.V.SME9327×
5Croonwolter&dros B.V.SME9325×
6SPIE Nederland B.V.SME9223×

05Tender documents

TN357115 - SF03 Aankondiging van een gegunde opdracht 20230828094635pdfAug 28, 2023 · 26 KB
IO punten RK ETdocxOct 13, 2022 · 41 KB
Visio-installatieschema HVK-2_HVK-2N_HNB-2 gebouw A165pdfOct 13, 2022 · 118 KB
Nota van inlichtingen 2022-10-13-4pdfOct 13, 2022 · 32 KB
Visio-installatieschema HVK-1_HVK-1N_HNB-1 gebouw A165pdfOct 13, 2022 · 122 KB
1e besteksaanvulling A165pdfSep 22, 2022 · 138 KB
B04 - brandcompartimentering 2de verd.pdfSep 22, 2022 · 501 KB
Bijlage 22 Visio-UPS ruimte 027 kabelwegenpdfSep 22, 2022 · 85 KB
Bijlage 18 - 32C35 CNA Advies Bodemkwaliteit & OO noodstroomaggregaat A165 2021 21392pdfSep 22, 2022 · 148 KB
Bijlage 21 Visio-UPS ruimte 027pdfSep 22, 2022 · 88 KB
Bijlage 17 - Beschrijving van een betreedbaar energiegebouwpdfSep 22, 2022 · 115 KB
B05 - brandcompartimentering 3de verd.pdfSep 22, 2022 · 508 KB

06Legal themes that may be relevant here

07Frequently asked questions

What is the scope of the assignment for the cooling and the data network?
The assignment includes the design, supply, installation, and testing of an efficient cooling system for critical IT infrastructure and the expansion of the existing data network with additional switches, cables, and redundant connections.
Which technical standards must the execution comply with?
The works must comply with Dutch safety and energy efficiency standards, including ISO 27001 compatibility for data security and the latest energy-efficient cooling technologies.
What is the focus on sustainability within this project?
The execution must align with the sustainability objectives of the ministry, with a specific focus on CO2 reduction and minimizing the ecological footprint.
What is expected of the contractor regarding project management?
The contracting authority expects the delivery of a detailed project plan, a schedule, a cost estimate, and a maintenance contract.

Automatically compiled from the official tender data and documents.

08Estimated value versus the market

p25
€ 1,4 mln
median
€ 3,6 mln
p75
€ 9,1 mln
€ 3,5 mln

Gegunde waarden in CPV 45 · werken n=3159