ClosedWorksEuropeanCompetitive dialogueGreen

22490 | Renovation/New Construction Green Gatwick in Amsterdam

Rijksvastgoedbedrijf · Competitive dialogue · 335115
Type
Works
45000000
Estimated value
Not published
To deadline
Ongoing
Knock-outs
0
exclusion grounds
Award basis
Best price-quality ratio
Assess manuallyconfidence high

This project concerns the integral design and realization task for the expansion and renovation of the Green Gatwick government office in Amsterdam-Sloterdijk.

Works · Competitive dialogue · European procedure

Sustainability countsEuropeanComplete timeline
Contracting authority
Contract type
Works
Competitive dialogue
Estimated value
Estimate not published
Submission deadline
Ongoing
09:00
Scope
European
European procedure
Lots
Single contract
Main CPV code
Location
Netherlands
CharacteristicsCPV 45WorksEU tenderGreen / SPPRijksvastgoedbedrijfGatwickstraatRenovation

01What is being requested

The integral design and realization of the expansion and transformation of the Green Gatwick building into a sustainable government office of approximately 47,000 m2 GFA by means of a Design & Build contract type.

In 2019, the RVB purchased a building on the Gatwickstraat in Amsterdam with the aim of, after expanding the building, relocating the government services from the Sloterdijk government office to the renovated building. 1. The RVB intends to expand this building and transform it into an attractive and sustainable government office. A government office that complies with the National Frameworks such as, among others, the Physical Working Environment Rijk (FWR) and the sustainability goals from the recently established Routekaart 2.0. 2. In addition, it is our ambition to have the new government

45000000Works

02Strategic insight

Strategic insight · AI analysis
Ensure conclusive evidence of the technical reference assignments in accordance with the specific requirements per competence. During application, pay close attention to joint and several liability in the submitted documents. Submit the Eigen Verklaring Sancties Rusland fully and signed to prevent exclusion.
Read automatically from the tender documents using AI. Always verify against the original documents.

03Points of attention

Important · 4
The realization takes place on a cramped construction site.Important
The existing concrete shell must remain intact.Important
Consideration must be given to the construction site layout and nuisance.Important
The agreement is concluded on the basis of UAV-GC 2005.Important

04Can I take part?

Technical · 3
Experience as a main contractor with a large-scale transformation: one reference assignment as a jointly and severally liable contractor for a large-scale renovation of at least 8,000 m2 GFA of a utility building, including disciplines of building physics, installation technology, and building technology, delivered within the term and no later than seven years ago.Technical
Experience as a main contractor/coordination responsible with 'special' integration: one reference assignment as a jointly and severally liable contractor for the realization and integration of a 'special' (such as a laboratory or research space) in a utility building, delivered within the term and no later than five years ago.Technical
Experience as an integral manager with an integrated process: one reference assignment as an integral manager (main contractor) for the design and realization phase (at least from DO to UO) of a large-scale renovation and/or new construction/extension of a utility building of at least 17,500 m2 GFA under integrated contract conditions such as UAV-GC or DBFMO, delivered within the tTechnical

05Exclusion grounds

Exclusion grounds — consult the ESPD
  • No specific exclusion grounds were extracted. In a European tender, the mandatory and discretionary grounds of art. 2.86/2.87 of the Dutch Procurement Act almost always apply — check the European Single Procurement Document (ESPD).

06Process & timeline

Information meeting application phase
29 augustus 2024
Deadline for submitting requests for further information application phase
6 september 2024, 23:59 uur
Publication of Memorandum of Information application phase
20 september 2024
Closing date for submitting application
1 oktober 2024, 9:00 uur
Communication of selection decision & appeal period
25 oktober 2024
Sending invitation to participate in the dialogue
4 november 2024
Final delivery date
21 mei 2029

07Value in context

Estimate not published

The contracting authority did not publish an estimated value — common for a large share of contracts. The EU threshold for werken is € 5,54 M, for reference.

08Likely competitors

#Likely bidderFitWins
1BAM Bouw en Techniek bvSME10036×
2Hegeman Bouw & Infra B.V.SME10031×
3BINX Smartility B.V.SME9927×
4Heijmans Utiliteit B.V.SME9833×
5Sweco Nederland B.V. SME9873×
6Arcadis Nederland B.V.SME96121×

09Tender documents

Nota van inlichtingen 2024-09-20-1pdfSep 20, 2024 · 18 KB
Aanbestedingsleidraad aanmeldingsfase concurrentiegerichte dialoog Green Gatwick v1.3 dd 20092024pdfSep 20, 2024 · 520 KB
Presentatie inlichtingenbijeenkomst Green GatwickpdfSep 20, 2024 · 2187 KB
Proces-verbaal van bezoek aan locatie 29 augustus 2024 Green GatwickpdfSep 4, 2024 · 99 KB
TN465715 - EF16 Aankondiging van een opdracht - algemene richtlijn, standaardregeling 20240712154129pdfJul 14, 2024 · 24 KB
Verklaring bestuurder Model KpdfJul 12, 2024 · 206 KB
(concept)Aanbestedingsleidraad dialoog en inschrijvingsfase concurrentiegerichte dialoog Green Gatwick v1.0pdfJul 12, 2024 · 382 KB
Eigen Verklaring Sancties RuslandpdfJul 12, 2024 · 127 KB
Regeling Scheiding van belang Rijksvastgoedbedrijf 16.1pdfJul 12, 2024 · 352 KB
Model opgave referentieopdrachtenpdfJul 12, 2024 · 168 KB
Inschrijvingsbiljet combinatiespdfJul 12, 2024 · 207 KB
(concept) Basisovereenkomst UAV-GC Renovatie en Nieuwbouw Green GatwickpdfJul 12, 2024 · 158 KB

10Legal themes that may be relevant here

11Frequently asked questions

What is the purpose of the renovation and expansion of the building on the Gatwickstraat?
The Rijksvastgoedbedrijf wants to expand the building and transform it into an attractive and sustainable government office. The goal is to relocate the government services from the Sloterdijk government office to this renovated building.
Which specific national frameworks must the new office comply with?
The new government office must comply with the National Frameworks, including the Physical Working Environment Rijk (FWR) and the sustainability goals from the Routekaart 2.0.
Which contract type is used for this project?
The assignment is requested as a Design and Build assignment under the UAV-GC.
What is the ambition regarding the sustainability performance of the building?
The ambition is to have the new government office perform exceptionally well, so that the sustainability goals of the State are amply achieved.

Automatically compiled from the official tender data and documents.